So i am on my way upstairs to the Grid to see how the demolition is going up there.
But wait, What the heck is this. Two large 2" conduits are running upstage from the plaster line. Why are these here. I thought that i was supposed to be consolted before anything is installed up here. NOOOOOOOOOO. Another five foot section that i wont be able to drop a point running all the way upstage from the plaster line. Why did this happen?
So it turns out that there was these two panels up there that are supposed to hold 3 phase motor power that we could plug into easily on the grid and if we are lucky we could even have control down at the stage managers panel if all goes correctly. But so far it is not looking good, this 2" conduit just can't be here. So now we have to figure out who's fault it is so that then we can figure out who is responsible for paying for fixing it. We don't have time for this silliness we just need to get it done and done right.